The following is a brief summary of construction events scheduled for Monroe Hall in the next few weeks. Dates and times could change somewhat based on weather conditions.

1. Demolition of the south stairway, which is currently in progress, should be completed in another 7-10 days.

2. Equipment will be mobilized and pilings delivered between December 5th and December 9th. Materials staging and other preparatory work will take place from December 10th -16th. Actual pile driving will begin on December 17th and continue through January 7th. Pilings  will be driven on both the north and south sides of the building, and work will be ongoing seven days per week with the exception of Christmas Day, December 25th.

3. On December 26th we will begin major underground utility work on Loyola Street, between Monroe Hall and Miller Hall. This work will require the presence of a crane and other large equipment. This work is expected to last through January 7th.

We will try to keep everyone informed if any major deviations from the planned schedule become necessary.

 

Sponsored Links: Check Out Latest Freshco Flyer, No Frills Flyer, Food Basics Flyer

Comments are closed.