The first phase of pile driving is now complete, pile driving equipment has been removed, and current work activities will have a much smaller impact on the occupants of Monroe and adjacent buildings.  Foundations are being prepared, concrete is being placed, and general cleanup necessary after moving the large equipment is underway.  After the foundation for the tower crane is complete, the next major activity will be the erection of the tower crane.  This crane will serve the job for the next several years, and will be a key component in the overall progress of the job.  Please continue to observe construction activities from outside of protective fencing and barricades, and help us maintain a safe site for workers and the entire Loyola Community.

 